Community Notice:

Please see below timeline for the next week regarding survey and water sampling for the Water Improvements project.

Apologies for the short notice, we were just given a timeline by Chatwin late Friday afternoon.

April 14: 9:30 am to 4:30 pm (survey work occurring on East Sooke Road or above the reservoirs) – work completed by Chatwin Engineering Ltd.,

April 15: 9:00am – 4:30pm (utility locates/traffic control work occurring on East Sooke Road and a portion of Sutiacum) – work completed by Kelly 1st Call Locates

April 16 & 17: 9:00 am – 2:00pm (boreholes drilled on East Sooke Road, the reservoir access road, the chlorination building access road and a portion of Sutiacum as part of the environmental assessment) – work completed by Tetra Tech

April 22: 9:00am – 2:00pm (groundwater sampling occurring on East Sooke Road, possibly a portion of Sutiacum) – work completed by Tetra Tech
This work is related to the water improvements project.